Projects
Pöhl dam – the smaller Thoßfell “pre-dam” - concrete repairs to the above and below the waterline
| The purpose of the Thoßfell and Neuensalz “pre-dams” of the Pöhl dam is to eliminate pollutants such as nitrates and phosphates, which are introduced by the high population density in the catchment areas. Another objective is the retention of sediments. The “pre-dams” are continuously kept full. A reduction in the water level or draining of the water is only done if necessary for repairs. Preliminary investigations by the Planning Office revealed serious defects in the existing concrete (alkali silica reactions) This clearly identified the building contract, replacement of old concrete (high-pressure water jet removal) and application of anchored, reinforced shotcrete in the zones subject to alternating water levels above and below the waterline. Due to the poor accessibility, the first step was the construction of a 350-metre-long construction site access, the preparation of a crane support surface and the laying of pipes for the drainage of inflows from the stilling basin. After removal of the damaged concrete by high-pressure water jet robots, reinforced shotcrete with hollow microspheres was sprayed on. Then followed the formation of construction joints, which were then sealed with a compression profile. |
|
|
|
![]() |
Installation of new reinforced shotcrete arches for two railway overpasses in Erkrath
|
The Reconstruction Division of SCHACHTBAU NORDHAUSEN GmbH was commissioned by the REGIO-Bahn GmbH with the reconstruction of two railway overpasses in Erkrath as part of the railway line Mettmann-Düsseldorf reconditioning. First step was the extensive removal of damaged brickwork up to 20 cm depth in one meter broad streaks by milling. To catch and remove leakage water, drainages were installed every two meter. As replacement for the removed brickwork a new, 20 cm thick shotcrete layer of water-proof concrete was applied. The concrete got a reinforcement that was fixed by anchors against the original, undamaged brickwork. In doing so, the structural stability and watertightness of the overpasses was reestabilished again. in total 82 m³ brickwork was removed and 340 m injection tubes for grouting were installed. For the construction of the replacement layer 3400 anchors, 7 t reinforcement steel and 115 m³ shotcrete had to be processed. During all stages of the construction works comprehensive safety precautions had to be taken, to avoid any danger for the onegoing pedestrain and bicycle traffic underneath the overpasses. |
![]() |
![]() |
![]() |
![]() |
Water reservoir Pöhl - Dam repair
|
|||
|
|
South Bridge Düsseldorf
|
SCHACHTBAU NORDHAUSEN GmbH was commissioned with the strengthening of the South Bridge Düsseldorf-Neuss in May 2004 (remark: the bridge was renamed in "Josef-Kardinal-Frings-Bridge" during construction period). The bridge actually consists out of three separated structures, the main bridge crossing the river Thine and two foreshore bridges either on the Neuss side and the Düsseldorf side. Within the three years of contract duration the strengthening was done by installation of 220tons steel beams (t-profile and standard I-profile) inside zhe box girder of the main bridge. For this the execution of 20 km welding seams was necessary. The bearing capacity of the foreshore bridges was improved by adding L-profile steel beams to the main and cross structure beams. Furthermore a 800 m long catwalk (covering 4.000 m² open mesh flooring) was attached to the bridge for easier maintenance and repair access. Together with the ongoing construction work beneath the bridge surface, the joints between the road surface sections were overhauled, 1.600 m crash barrier were installed and the handrail was raised to 1.2 m in height. During all stages of the construction work the unobstructed traffic crossing the bridge had to be guaranteed. |
THE SQUAIRE FRANKFURT – structural upgrading and restoration of welded seams
|
In the largest continental hub of international air traffic directly above the ICE railway station, the most mobile workplaces of our time – THE SQUAIRE centre Frankfurt. The building is located right in the middle of the B 43 and BAB 3.
|
![]() |
![]() |
![]() |
Rhine River bridge Leverkusen BAB A 1 - reinforcement of the superstructure
|
The above-mentioned road bridge is where the federal motorway A1 crosses over the Rhine River. The actual steel bridge features a 700-metre long cable-stayed bridge with two box girders and orthotropic deck. |
![]() |
|
|
Ahrtalbridge BAB A 61 repairs to underside and substructures of bridge
| The federal motorway BAB 61 crosses the Ahr valley at a maximum height of 54 metres. The superstructures designed as a continuous girder per carriageway dating from 1976 are 1,521 metres long and consist of 22 sections with lengths of between 45 m and 106 m. Broken out concrete areas with exposed reinforcement, exposed tendons, honeycombing and cracks on the coupling joints represent the damage symptoms. To ensure the safety of traffic below the bridge all concrete defects had to be eliminated. By trimming the existing board structure and a subsequent protective coating of the outside surfaces of the superstructure and pier heads, should provide the structure the necessary durability. The repairs on the piers and abutments were carried out from stationary scaffolding with safety nets. Concrete preservation measures on the pier shafts were limited to damaged areas. An OS-C coating was only applied to the top 6 metres of the pier heads. Repairs on the superstructure were carried out from two movable, water and wind-proof suspension scaffolds. Work cycles: - Expose damaged areas, remove formwork anchors - Dismantle bridge drainage - Grind down board structure and high-pressure water jets up to 1000 bar - Re-profiling of individual damaged areas - Repairs on the pier heads - Apply an OS c coating to the bridge underside, abutments and pier heads - Apply an OS B coating to the caps - Dismantle bridge drainage Main mass About 100,000 square metres of concrete surface were examined as part of repair measures: Service: 71,600 m² OS-C; 5,000 m² OS-B; re-profile 990 m² individual damaged areas, replace 500 m bridge drainage to the main pipeline, blast 167 pieces drainage pipe and apply corrosion protection. Materials: 486 t fine filler, 20 800 l coating material; 160 t blasting media, 97 t shotcrete and 75 t of heavy mortar. |
| |













