Projects
Demolition and reconstruction of the Schnettker bridge, Dortmund, B1, construction of rainwater retention basin as well as earthwork and canal and cover structure construction for the ramps
|
The actual construction work began at the beginning of 2006, after the award of the contract and the ceremonial groundbreaking in September 2005. The construction assignment was to replace the existing “Schnettker bridge” structure with a new structure between Bochum and Dortmund as a part of B1. - Preparation of a verifiable construction analysis and ready-for-construction documents,
|
![]() |
![]() |
![]() |
B 188n, Rathenow bypass
|
Construction of B 188n along with a bridge structure over the river Havel was start at the beginning of 2008 and to be carried out as a part of the Rathenow bypass from 31803.00 to 0+181.250 construction kilometer.
The existing structure, a railway flyover constructed in the year 1926, was to be completely demolished. The propose bridge structure number 5-1 was constructed as a bow-string arch girder bridge with continuous composite approach spans (continuous composite structure) with a spread footing supported substructure. The bow-string arch girder bridge with its exterior arches has a maximum span length of 90 m and the total length of the construction is 203.40 m. Both abutments have service walkways enabling access to the steel box girders and maintenance of the multi-cell expansion joint. In September 2009, the bridge was longitudinally launched during a 48 hour blockage of shipping traffic on the Havel river. The stiffness of the steel box girdle calculated for the final state allowed to cantilever the superstructure during launch of all spans with the exception of the main span. For this part, a barge was used for support Pouring the cast-in-place concrete deck slab was done by alternating pouring sequence method. The for north-western Brandenburg unusually harsh winter of 2009/2010 as well as additional services required for road construction led to an opening of the bridge on 31.08.2010. The bypass and Havel bridge on B 188n were subjected to an “initial test” with the Havel Bridge Race on 28.08.2010 and inaugurated worthily. |
||
![]() |
![]() |
|
|
|
A10, structure 72, demolition and renewal including ramp adjustment
As part of a joint venture, the civil engineering division constructed structure number 72 over the river Havel near Brieselang. Earth and road work construction are executed by the ARGE [joint venture] partner.
The construction of this replacement structure is being implemented in two construction phases with the aim of enabling the expansion of the federal motorway to three lanes in each direction.
The earthwork began in early 2009. First, a one-sided extension of the embankment with expansion of both ramps was required.
The first part of the structure was preassembled on the new south-eastern embankment. Huge substructures were being constructed simultaneously. The foundations were made from under water concrete in closed sheet pile boxes.
The bridge was shifted over the river Havel with the aid of a barge and self-propelled modular transporters (SPMTs).
All motorway traffic was diverted to the 1st part of the structure once the road access was completed. Next, the existing structure was demolished. Subsequently, the second part of the structure was constructed.
Once the foundations are completed, the bridge is to be shifted analogous to the 1st construction phase in June 2011.
Both parts of the structure are bow-string arch girder bridges with crossed round steel hangers.
This required extreme precision during production in the fabrication facilities in Nordhausen as well as during the assembly on site. As intended, all targeted quality goals were met.
The total weight of both steel bridges (without cast-in-place concrete deck slabs) is about 1800 t.
Opening for traffic is planned for late autumn of 2011.


| As part of a joint venture, the civil engineering division constructed structure number 72 over the river Havel near Brieselang. Earth and road work construction are executed by the ARGE [joint venture] partner. The construction of this replacement structure is being implemented in two construction phases with the aim of enabling the expansion of the federal motorway to three lanes in each direction. The earthwork began in early 2009. First, a one-sided extension of the embankment with expansion of both ramps was required. The first part of the structure was preassembled on the new south-eastern embankment. Huge substructures were being constructed simultaneously. The foundations were made from under water concrete in closed sheet pile boxes. The bridge was shifted over the river Havel with the aid of a barge and self-propelled modular transporters (SPMTs). All motorway traffic was diverted to the 1st part of the structure once the road access was completed. Next, the existing structure was demolished. Subsequently, the second part of the structure was constructed. Once the foundations are completed, the bridge is to be shifted analogous to the 1st construction phase in June 2011. Both parts of the structure are bow-string arch girder bridges with crossed round steel hangers. This required extreme precision during production in the fabrication facilities in Nordhausen as well as during the assembly on site. As intended, all targeted quality goals were met. The total weight of both steel bridges (without cast-in-place concrete deck slabs) is about 1800 t. Opening for traffic is planned for late autumn of 2011. |
||
![]() |
![]() |
|
|
|
Construction of B6n, BA 13.3 road and bridge construction
The route of the future B6n runs north of Ilberstedt and crosses a double track railway line.
Within a joint venture partner, the Civil Engineering Division is working as a contractor for SCHACHTBAU NORDHAUSEN Großprojekte GmbH.
This subsidiary of SCHACHTBAU NORDHAUSEN GmbH is responsible for constructing the 93A structure over the railway line.
What makes this structure unique, is its location is in a region of mining subsidence.
According to prognoses, subsidence of up to 5 m is to be expected in this area in the next 100 years.
To compensate for this, the project owner decided to construct a 92 m long steel truss bridge for each direction of traffic.
The total steel weight of these structures amounts to 1564 t.
The bridge will be shifted during a complete closure of the railway track by means of self-propelled modular transporters (SPMTs). For this purpose, a travel path made of steel steel mats will be constructed from one to the other abutment in order to protect the track of DB Netz AG.
The cast-in-place concrete decks will be installed after the truss bridges have been set.
The opening for traffic is to take place in December 2011.
Thus, B6n will be continuously open to traffic from motorway A 14 up to motorway A 395 and Goslar.


| The route of the future B6n runs north of Ilberstedt and crosses a double track railway line. Within a joint venture partner, the Civil Engineering Division is working as a contractor for SCHACHTBAU NORDHAUSEN Großprojekte GmbH. This subsidiary of SCHACHTBAU NORDHAUSEN GmbH is responsible for constructing the 93A structure over the railway line. What makes this structure unique, is its location is in a region of mining subsidence. According to prognoses, subsidence of up to 5 m is to be expected in this area in the next 100 years. To compensate for this, the project owner decided to construct a 92 m long steel truss bridge for each direction of traffic. The total steel weight of these structures amounts to 1564 t. The bridge will be shifted during a complete closure of the railway track by means of self-propelled modular transporters (SPMTs). For this purpose, a travel path made of steel steel mats will be constructed from one to the other abutment in order to protect the track of DB Netz AG. The cast-in-place concrete decks will be installed after the truss bridges have been set. The opening for traffic is to take place in December 2011. Thus, B6n will be continuously open to traffic from motorway A 14 up to motorway A 395 and Goslar. |
||
![]() |
![]() |
|
|
|
Motorway A 38
Bridge over Rhin valley and B 80
|
The federal motorway A 38 crosses the Rhin valley and the today’s State Road 3080 west of the Höllberg tunnel, thus making the construction of a 307 m long bridge necessary. This was achieved with the following span lengths: 32– 41– 46– 60– 46– 44– 38 m. |
||
|
|
|
|
|
|
Reconstruction of EÜ Hösbach
|
The railway overpass is a part of the double track Würzburg – Aschaffenburg line and crosses over the motorway A3 in Hösbach. The structure was put out for tender by DB ProjektBau GmbH NL Frankfurt/Main as a network arch superstructure. - Support width 95.65m The superstructures were fabricated from September 2010 to December 2010 in Nordhausen in constructional segments with a transportable weight per unit of up to 60 t. |
||
![]() |
![]() |
|
|
|
Reconstruction of the Walddörfer bridges in Hamburg
Underground railway construction of HOCHBAHN AG
|
The existing bridge structures D(37), D(38), D(40) and D(44) in the northern section of the U1 route of the Hochbahn AG in Hamburg were replaced with new substructures and superstructures. The work was done in the summer of 2009 while the double track route was closed to traffic for eleven weeks. Four steel superstructures weighing from 45 to 95 tonnes each were entirely fabricated and color-coated in the work shop of SCHACHTBAU NORDHAUSEN GmbH, then transported to the construction site with maximum measurements of 7.25 m width by 24.80 m length, and subsequently mounted with mobile cranes. The final transport of the superstructure for BW D(37) from the assembling lot to the bridge location was carried out with the help of SPMT modules. All other superstructures could be placed directly.
Activities performed • Disassembly and disposal of the existing superstructures D(37), D(38), D(40) and D(44)
• Fabricating, color-coating and direct assembly of the constructions D(38), D(40) and D(44) with 500t or 800t mobile cranes. • Fabricating, assembly, site color-coating and final launch of the D(37) construction with SPMT modules • Incidental construction for all individual structures The total weight of all the steel construction troughs for all the four constructions is 418 t.
|
||
![]() |
![]() |
|
|
|
Maintenance of the Strelasund Bridge
|
The Strelasund Bridge connects the Rügen and Dänholm islands near Stralsund. The bridge was constructed in 1936/37 and is being restored by the Department of Transportation since 1994. In 2009, Stralsund’s Road Construction Office called for tenders for rehabilitation of the bridge deck. It consisted of 47.5 m orthotropic slabs and 492.5 m reinforced concrete slabs. Demolition: Lengthwise separation of the reinforced concrete deck with the help of concrete saws, cutting of the longitudinal girder underneath the motorway and hauling of individual concrete slabs Renovation: Preparation of the existing cross beams for bolted inserts for proposed connection with the new cross beams and attached deck panel, demolition of consoles on cross beams and main girders, preparations for construction of the new deck structure Reconstruction: Lifting of the new deck structure consisting of two edge segments and a central segment, each 10.80 m long, assembly with 100 t mobile cranes, weight approx. 21 t,
Girder bridge Individual span length / total length: 54 m / 540 m Distance between the curbs: 6.50 m Deck surface: 3510 m² New deck construction: 899 t S235 and S355 Construction time 05/2010 to 12/2011
|
||
![]() |
![]() |
|
|
|




















